Woodlands · 230 kV Power + Auxiliary · Nostag 10
Took over the project mid-stream for SP Group and LS Cable & System after the previous contractor walked off halfway. Dimension completely remobilised the vessel — reel-drive and full cable-lay system — drove the MWS approval cycle, rebuilt the project procedures and mobilised & operated the Vertical Injector in 3 months, on the Singapore – Malaysia 230 kV Woodlands interconnector.
The previous contractor walked off the Singapore – Malaysia Woodlands interconnector with the project halfway through. Dimension was brought in by SP Group and LS Cable & System to take over and rescue the programme — completely remobilising the vessel with reel-drive and a full cable-lay system, driving the MWS approval chain, rebuilding the project procedures from scratch, and mobilising and operating the Vertical Injector for cable burial. Three months from takeover to back offshore.
SP PowerAssets (SP Group) and Tenaga Nasional Berhad (TNB) commissioned two new 230 kV cable circuits — land and submarine — to strengthen the interconnection between the Singapore and Malaysian power networks. LS Cable & System was the main contractor for supply and installation of the two circuits and auxiliary cables across the Straits of Johor, from Woodlands, Singapore to Johor Bahru, Malaysia.
Mid-programme, the original installation contractor demobilised. Dimension was brought in by SP Group and LS Cable & System to take over and rescue the project — completely remobilising the Nostag 10 with the reel-drive and cable-lay spread, driving the MWS approval cycle, rebuilding the project procedures and mobilising and operating the Vertical Injector for cable burial. The recovered programme was returned to offshore operations in 3 months.
| Parameter | Value |
|---|---|
| Power Cable Type | LS-230 kV 1C 2500 SQ |
| Power Cable Outer Dia. | 179 mm |
| Power Cable Dry Weight | 81 kg/m |
| Aux Cable 1 Type | Optical, 20-pair telephone & 10-core LV |
| Aux Cable 1 Outer Dia. | 44.9 mm · 78.1 mm · 63.4 mm |
| Aux Cable 1 Dry Weight | 4.2 kg/m · 12 kg/m · 8.1 kg/m |
Mid-project takeover — Nostag 10 fully remobilised in 3 months after the prior contractor demobilised.
Whole MWS approval cycle and project procedures rebuilt under Dimension's name to release offshore operations.
Vertical Injector mobilised and operated for cable burial on the same compressed window.
Critical cross-border 230 kV power interconnect between SP Group (Singapore) and TNB (Malaysia) returned to schedule.
Talk to our engineering team about feasibility, FEED, equipment supply or offshore execution support.