Geo Caspian — Skipsteknisk CD · Turnkey Conversion to a Carousel-Equipped Cable Lay Vessel
A 24 m beam sister hull to Geo Celtic, delivered by Dimension as a turnkey conversion through partner shipyards, with leading vendor support across the mission spread — ≈3,600–4,000 t of fibre-optic cable (3,400 t carousel plus 600 t spare tanks), or ≈2,500 t of power cable — with 167 t continuous bollard pull, the highest in the fleet, and dedicated inter-array cable (IAC) handling. The complete fibre-optic mission spread is supplied new.
Teal-flagged items in the specification below denote new or modified equipment within the conversion scope.
A near-sister to Geo Celtic, sharing the same 24 m beam and 20.5 m carousel arrangement — but with the fleet's highest bollard pull at 167 t and a dedicated power-cable spread, making ST327L the candidate of choice for combined lay, burial and inter-array cable (IAC) scope.
| Principal Particulars | |
| Design | Skipsteknisk CD |
|---|---|
| Built | 2010 · Fosen Mek, Norway |
| Length overall | 108 m |
| Beam, hull / extreme | 24.0 / 28.0 m |
| Max draught | 7.5 m |
| Gross tonnage | 12,708 |
| Deadweight | ≈5,960 t |
| Fresh water production | 50 m³/day |
| Cable Capacity — Converted | |
| Installed tank capacity | 3,400 t carousel + 600 t small · ≈4,000 t installed · Ø20.5 m |
| Fibre-optic cable, working load | ≈3,600 – 4,000 t |
| Power cable capacity | ≈2,500 t |
| Stowage form | Below-deck carousel |
| Power & Propulsion | |
| Main generators | 2 × 4,320 + 4 × 1,665 kW |
| Total installed power | ≈15,300 kW |
| Propulsion | 2 × 4,500 kW, CPP in nozzle |
| Bow thruster | 2,000 kW tunnel |
| Stern thruster | 1,200 kW — new |
| Retractable azimuth | 2,200 kW |
| Energy storage | 1,500 kWh ESS — new |
| Performance, Accommodation & Class | |
| Max / cruising speed | 16 / 14 kn |
| Endurance | 39 days at sea |
| Fuel / fresh water | 2,450 / 475 m³ |
| Continuous bollard pull | 167 t |
| Dynamic positioning | DP2 — retrofit |
| Persons on board | 70 single cabins, plus hospital |
| Classification | DNV · Clean(Design) · DK(+) |
| Cable Handling & Deck — All New | |
| Carousel, below deck | Ø20.5 m · 3,400 t FO |
|---|---|
| Lay & burial ROV | SMD QT600 |
| Burial depth | 3.0 m · 2,500 msw · 450 kW |
| Drum cable engine | SMD, Ø4.0 m, 40 t |
| DOHB | 4 wheel-pair, 4 t |
| Stern sheaves | 2 × Ø3.5 m |
| Power cable spread | 30 t quadrant · 5 t and 15 t tensioners |
| Plough | SMD MD3-XT |
| Plough trench depth | 3.3 m · 80 te tow load |
| Plough LARS | A-frame 60 – 100 t SWL |
| Work-class ROV | 2,000 m rated, with LARS |
| Lay control | Makai Lay + Plan · ROV-referenced |
Prepared September 2026. Subject to inspection and final equipment selection.
Talk to our engineering team about feasibility, acquisition structuring or the fibre-optic mission-spread scope.